Read the Financials Page
The Financials page on the web app shows how all your projects are doing on one screen: how far along they are, labor hours, profit, and estimate versus actual costs.
Who can use it
Owners, Administrators and Managers. Click Financials in the left sidebar. Members don't see it.
The page opens with Welcome and your name at the top, then the filters, four gauges and two bar charts.
Filters
Every gauge and chart follows all of the filters.
| Filter | What it does |
|---|---|
| Select Project | Shows only the projects you pick. |
| Select Status | Active or Inactive. The page opens set to Active. |
| Select COGs | Materials, Labor or Trade Partners. |
| Select Cost Group | Shows only the cost groups you pick. |
| Select Contract Type | Fixed Cost, Cost Plus or All. |
| Select Project Type | Shows only the project types you pick. |
| Date Range | Limits expenses by their date, and change orders by the date their status last changed. Estimates are never limited by date. |
When you pick a project, Buildwise clears Select Status, Select Contract Type and Select Project Type. That way an Inactive project still shows when you pick it. Clear the project and Select Status goes back to Active.
Filters reset each time
The filters go back to these starting choices each time you open the page.
Picked a Date Range?
Spending and change orders are limited to those dates, but the estimate is not. So a one-month range compares one month of spending with the whole estimate, and PERCENT COMPLETE and the bar charts will look low.
What counts
- Estimates and change orders that are Client Approved or Manually Approved. Drafts, released ones still waiting for approval, and declined ones are left out.
- Every project expense, billable and unbillable.
- Overhead expenses are never counted.
- The Lunch cost group is never counted.
PERCENT COMPLETE
What you have spent, divided by what you expect to spend, across every project and cost group the filters show. What you expect to spend depends on the Contract Type:
| Contract Type | Expected to spend, for each cost group |
|---|---|
| Fixed Cost | The approved estimate + approved change orders. |
| Cost Plus | The larger of the budget (approved estimate + approved change orders) and what was spent. Once the cost group is marked complete, both spent and expected are its billable expenses only. |
Example on a Cost Plus project:
| Cost group | Budget | Spent | Expected |
|---|---|---|---|
| Framing | $10,000.00 | $6,000.00 | $10,000.00 (the budget is larger) |
| Electrical | $5,000.00 | $7,000.00 | $7,000.00 (spent is larger) |
| Total | $15,000.00 | $13,000.00 | $17,000.00 |
PERCENT COMPLETE = $13,000.00 ÷ $17,000.00 = 76.47%. It shows 0.00% when the expected amount is $0.00.
Example on a Fixed Cost project: the Framing cost group has an approved estimate of $3,000.00 for labor + $5,000.00 for materials = $8,000.00. $1,350.00 of labor and $5,250.00 of materials were spent, so $6,600.00 ÷ $8,000.00 = 82.50%.
LABOR HOURS
The big number is the hours on Labor expenses. The right end of the gauge is the hours planned on the Labor lines of approved estimates and change orders. A labor credit on a change order takes hours off the plan.
As an example, 120 estimate hours + 20 change order hours = 140 hours planned. If your team has worked 150 hours, that's more than planned, so the needle is in the red.
The gauge turns gray when Select COGs is set and doesn't include Labor.
Gauge colors
| Color | PERCENT COMPLETE and LABOR HOURS |
|---|---|
| Green | Up to 75% of the target. |
| Yellow | From 75% to 100% of the target. |
| Red | From 100% to 120% of the target. The needle stops at 120%. |
GROSS PROFIT MARGIN has one green arc from 0% to 50%. The needle stops at 50%, and at 0% when the margin is below zero, but the number under the gauge always shows the real percent. To see how it and COGs + MARGIN are worked out, see How Gross Profit Margin and COGs + Margin Are Worked Out.
Estimate to Actual charts
Estimate to Actual Project Costs (by Project) has one set of bars for each project. Estimate to Actual Project Costs (by Cost Group) has one set for each cost group.
| Bar | What it shows |
|---|---|
| Actual (green) | All expenses, before markup and tax. |
| Estimated (dark blue) | Approved estimates. |
| Change order (light blue) | Approved change orders, stacked on top of Estimated. |
The biggest Actual comes first. With more than 15 sets of bars, scroll the chart sideways. Names longer than 16 letters end in "...".
Hover over a bar to see the full name and that bar's amount. Bars at $0.00 are left out.
If a box says Not Found or Server Error
That gauge or chart couldn't load. Refresh the page. If it still shows, click the round message button in the bottom-right corner of this page, then click Send a message.
💬 Have a question? Click the round message button in the bottom-right corner of this page, then click Send a message. We usually reply within a few hours.