Team Member Pay and Charge Rates
Each team member has a pay rate and a charge rate. Buildwise uses the pay rate to work out what each labor hour costs you. The charge rate is what you charge a client for an hour of their work on Cost Plus projects.
Where to find them
Click Settings at the bottom of the left sidebar and scroll to the Members list in the Team section. Look for the Pay Rate $ and Charge Rate $ columns.
Set the pay rate
A pay rate is required. You can't add a team member without one. Type it in the Pay Rate $ box when you add them. It saves by itself.
To work out a fully burdened pay rate, use the Labor Burden Worksheet. Need help filling it out? Click the round message button in the bottom-right corner of this page, then click Send a message.
Change the pay rate
Open Change Pay Rate
Click the Pay Rate $ box for the team member. The Change Pay Rate window opens.
Type the new rate
Type the new rate and click Save. The window shows the date it starts. A new pay rate starts at the beginning of the next pay period.
Until then, an info icon (a circle with an i) shows in the Pay Rate $ column. Point at it to see the new rate and the date it starts. When it starts, it's used on all active projects from then on. Labor already entered keeps the old rate. For pay periods, see Set Up Labor and Workweek.
Entered the wrong pay rate?
If you entered the wrong pay rate when you set someone up, we can reset it for you. Click the round message button in the bottom-right corner of this page, then click Send a message, and send us the team members and their correct pay rates. A reset changes all past labor for that team member. We can't change records one at a time, for a set period, or by project. See What happens if I've entered the wrong pay rates?.
Set the charge rate
Type it in the Charge Rate $ box. It saves by itself. Charge rates only apply to Cost Plus projects.
Don't leave it blank
If you leave the charge rate blank, it stays at 0. On Cost Plus projects, that person's time is then charged at $0 an hour. Enter a charge rate for everyone who works on Cost Plus projects.
Change the charge rate
Changing the charge rate in Settings only sets it for projects you create from now on. It doesn't change projects you already have.
To change it on a project you already have, open the project's Overview tab and change it in the Members section. The new rate is used for time entered from then on.