Project Schedules


Each project has a Schedule tab where you plan the work in phases and tasks. You can share it with your team and your clients.

Build a schedule

1

Open the Schedule tab

Open the project and click the Schedule tab. Use the arrow at the right end of the project tabs if you don't see it.

The Add button and the Phase/Task list on the Schedule tab
2

Add phases and tasks

Click Add to add to the schedule. Phases, like Superstructure, group the tasks under them. Click the arrow next to a phase, or use Expand all and Collapse all, to show or hide its tasks. Drag the handle at the left of a row to move it.

3

Change the view

Use Zoom in, Zoom out and Zoom to fit to change how much of the timeline you see.

Change a task's color

Double-click a task bar on the chart to open the Task Information window. On the General tab, click Color.

The Color field on the General tab of the Task Information window

Pick Blue, Dark Blue, Orange, Teal, Purple, Green, Red or Gray, then click Save.

The list of task colors

Link tasks with dependencies

A dependency ties a task to another task, so it starts or finishes based on that task. As an example, framing depends on foundation. The arrow on the chart shows the link.

The arrow that links the foundation task to the framing task
1

Open the task

Double-click the task bar on the chart to open the Task Information window.

2

Add the dependency

Click the Dependency tab, then click Add. A new row opens.

A new dependency row with Name, Type and Offset
3

Pick the task it depends on

In Name, pick the other task.

4

Pick the type

In Type, pick how the two tasks connect. See the chart below.

5

Set the offset

In Offset, enter a number of days to add a gap between the tasks. Enter a negative number to let them overlap. As an example, -2 days lets framing start before foundation is done.

6

Save

Click Save. The dependency shows on the Dependency tab with its type and offset.

A saved dependency on the Dependency tab
Type What it means
Finish-Start This task starts when the other task finishes.
Start-Start This task starts when the other task starts.
Finish-Finish This task finishes when the other task finishes.
Start-Finish This task finishes when the other task starts.

To remove a dependency, click its row on the Dependency tab, click Delete, then click Save.

Set how phase bars look

Click Settings in the left sidebar. Under Preferences, use Schedule Phase Bars to pick how phase bars look on your project schedules: Filled, Light Gray or Outline. Click Save at the bottom of the page.

The Schedule Phase Bars setting under Preferences

Start from a template

Have a schedule on another project you want to reuse? Click Copy From Template, pick the Project to copy from, and click Copy.

The Project field and Copy button in the Copy From Template window

Gantt and Calendar views

Click GANTT to see the schedule as bars on a timeline, or CALENDAR to see it on a calendar. In the Calendar view, pick Day, Week, Work Week, Month or Agenda.

The Gantt and Calendar buttons and the calendar view options

Share the schedule

Use Copy Url, Share By Email, Download or Client Preview at the top of the Schedule tab to share it or see what your client sees.

The Copy Url, Share By Email, Download and Client Preview buttons

Watch the tutorial

If you have any questions or need support:

💬 Click the beacon on this page to chat with us
📩 Click the beacon on this page to email us

Did this answer your question? Thanks for the feedback There was a problem submitting your feedback. Please try again later.

Still need help? Contact Us Contact Us