Project Schedules

Each project has a Schedule tab where you plan the work in phases and tasks. You can share it with your team and your clients.

Build a schedule

1

Open the Schedule tab

Open the project and click the Schedule tab. Use the arrow at the right end of the project tabs if you don't see it.

The Schedule tab on a project
2

Add a task

Click Add. Without a row selected, the new task goes at the bottom. With a phase selected, it goes under that phase.

The Add button on the Schedule tab
3

Fill in the task

The New Task window starts with today's date and the color Blue. Type the Phase/Task name, pick the Start Date and End Date, then click Save. Duration is worked out from the two dates.

The New Task window
4

Arrange your phases and tasks

Drag the handle at the left of a row to move it under a phase. Click the arrow next to a phase, or use Expand all and Collapse all, to show or hide its tasks.

5

Change the view

Use Zoom in, Zoom out and Zoom to fit to change how much of the timeline you see.

Zoom in, Zoom out and Zoom to fit

How phases work

  • A schedule has two levels: a phase, like Framing, and the tasks under it. A task can't sit under another task.
  • A phase's dates follow its tasks. It starts on the earliest task and ends on the latest one.
  • Moving a phase moves its tasks with it.
  • A phase's Progress comes from its tasks, weighted by how long each one is. As an example, a 1-day task at 100% and a 2-day task at 60% make the phase 73%.

How dates work

The work week is Monday to Friday. Weekends are shaded on the chart and aren't counted, and there are no holidays. Duration is in work days.

As an example, a 3-day task that starts Thursday Nov 5, 2026 runs Thursday, Friday and Monday, and ends Monday Nov 9.

A weekend shaded on the chart

Tasks can't start before the project

No task can start before the project's Start date. If a task already starts earlier, for example from a copied schedule, that earlier date becomes the limit. A project with no Start date has no limit, and there's no latest date.

Change a task's color

Double-click a task bar on the chart to open the Task Information window. On the General tab, click Color. Pick Blue, Dark Blue, Orange, Teal, Purple, Green, Red or Gray, then click Save.

The Color box in the Task Information window

Link tasks with dependencies

A dependency ties a task to another task, so it starts or finishes based on that task. As an example, joists depend on posts and beams. The arrow on the chart shows the link.

1

Open the task

Double-click the task bar on the chart to open the Task Information window.

2

Add the dependency

Click the Dependency tab, then click Add. A new row opens.

3

Pick the task it depends on

In Name, pick the other task.

4

Pick the type

In Type, pick how the two tasks connect. See the table below.

5

Set the offset

In Offset, enter a number of work days (Monday to Friday) to add a gap between the tasks. Enter a negative number to let them overlap.

6

Save

Click Save. The dependency shows on the Dependency tab with its type and offset.

The Dependency tab in the Task Information window
Type What it means
Finish-Start This task starts when the other task finishes.
Start-Start This task starts when the other task starts.
Finish-Finish This task finishes when the other task finishes.
Start-Finish This task finishes when the other task starts.

As an example, Posts and Beams ends Friday Nov 20 and Joists is linked Finish-Start. If Joists starts Monday Nov 23, the offset is 0 days, because the weekend doesn't count. If it starts Wednesday Nov 25, the offset is 2 days.

Moving a linked task

When you move a task, the tasks linked to it keep their dates. Buildwise changes the offset to match instead of moving them.

To remove a dependency, click its row on the Dependency tab, click Delete, then click Save.

Set how phase bars look

Click Settings in the left sidebar. Under Preferences, use Schedule Phase Bars to pick Filled, Light Gray or Outline. Click Save at the bottom of the page. This style changes phases left on the automatic Blue or Gray. A phase you gave another color keeps that color.

The Schedule Phase Bars choices

Start from another project's schedule

1

Open Copy From Template

Click Copy From Template at the top of the Schedule tab.

The Copy From Template button
2

Pick the project

In Project, pick the project to copy from, then click Copy.

The Copy From Template window
3

Confirm

If this project already has tasks, you're asked first, because copying replaces this project's whole schedule. Click OK to go ahead.

The warning before a schedule is replaced

Phases, tasks, colors, notes, progress, assignees and dependencies all come across. Every date moves by the same number of days, so the first task starts on this project's Start date, or today if there's none.

As an example, the template's first task starts Monday Mar 2, 2026 and this project starts Monday Nov 16, 2026. Every date moves 259 days, so a task from Mar 2 to Mar 4 becomes Nov 16 to Nov 18. Because whole calendar days are counted, a copied task can land on a weekend if the gap isn't a whole number of weeks.

Share the schedule

Use Copy Url, Share By Email, Download or Client Preview at the top of the Schedule tab.

Copy Url, Share By Email, Download and Client Preview

Share By Email fills in your client's emails, the subject "Schedule from [your company]" and a message with the link. Download saves a PDF of the chart.

The Share By Email window

Anyone with the link can see the schedule without logging in, but can't change it. It never shows money. The link always shows the schedule as it is right now, so a link you sent last month shows today's tasks.

What your client sees

Who can change a schedule

Anyone at your company who can open the project can add, change, move and delete tasks, Members with Job Access included. If two people save at the same moment, one of them is asked to reload the page.

Watch the tutorial

💬 Have a question? Click the round message button in the bottom-right corner of this page, then click Send a message. We usually reply within a few hours.

Did this answer your question? Thanks for the feedback There was a problem submitting your feedback. Please try again later.

Still need help? Contact Us Contact Us