Change Order Statuses

Overview

This article defines the five statuses associated with change orders in Buildwise, where to find them, and what happens when you change a change order's status.

Status Definitions

Notes

  • A change order must have either a Manually Approved or Client Approved status for Buildwise to add the costs to your project reporting. 
  • While a project can have only one approved estimate, it can have multiple change orders with Manually Approved or Client Approved status.
  • The status of a change order is linked to the document Lock functionality. For details, refer to the article Lock an Estimate or Change Order.
Status Description Notes

Draft is the default status of a newly created change order. The change order remains in Draft status until it is either manually changed, shared through Buildwise to your client, or approved by your client through Buildwise.
  • Change order is editable
  • Unlocked by default but can be locked at any time
  • Status can be changed at any time

Status is automatically updated to Released when the change order is shared with clients through Buildwise. Refer to the article Share Change Orders.

You can also manually select the Released status if you shared the change order directly through a PDF download or by sharing a web link with your client.


Manually Approved status is selected to indicate the client has approved the change order. However, we strongly recommend that your client digitally sign the change order through Buildwise to create a legally binding agreement. Refer to the article Change Order Signatures.

Status is automatically updated to Client Approved when the change order is digitally signed by the client through Buildwise. 

Note: You cannot select this status, as it can only be initiated through digital signing.

Declined status is selected manually to indicate the client declined the change order. This status cannot be updated.

View Change Order Status

The status of a change order is displayed in three locations: on the Buildwise Change Orders dashboard, the Project Change Orders dashboard, and on the specific change order page. 

Change Orders Dashboard

In the left sidebar, click Change Orders. The Change Orders dashboard lists change orders for all Active projects. The status is displayed in the Status column for each change order.

Project Change Orders Dashboard

On the project dashboard, click the Change Orders tab. The status is displayed in the Status column for each change order within the project.

Project Change Order

The status is displayed on the project Change Order.

Change the Status of a Change Order

Buildwise will automatically change the status when you share a change order with your client and when they digitally sign the document through Buildwise. You can also manually change the status using the status dropdown. 

The change order status can be changed on any of the change order page tabs: Items, SOW, or Share.

Click the status dropdown to select the new status.  

Depending on the current status of a change order, a warning confirmation popup may open. The table below shows what to expect when you manually change the status of a change order.

Warning: Once a change order is changed to Declined, the status cannot be updated. If you’ve selected this status in error, you can copy it by creating a new change order and using the Copy From functionality.

From status >> To status
Draft Any status

You can manually update the status of a Draft document to Released, Manually Approved, or Declined at any time.

Note: If you select Declined, you will not receive a warning confirmation.

Released Manually Approved You can select Manually Approved status to indicate approval within Buildwise. 
Released Draft

If you revert the Released status to Draft, a Warning! confirmation popup opens:

Warning! This Change Order has been released to your client. Are you sure you want to update?

Click OK to confirm.

Released Declined

If you change the status of a Released document to Declined, a Warning! confirmation popup opens:

Warning! By unlocking you risk changing your baseline estimate for all financial reports

Click OK to confirm.

Manually Approved

or

Client Approved

Draft

or

Released

Note: You can only change the status of Manually Approved or Client Approved change orders in projects that have no expenses.

If you change the status of a Manually Approved or Client Approved document to Draft or Released, a Warning! confirmation popup opens:

Warning! This Change Order has been approved by your client.

Are you sure you want to revert this to [Draft/Released] mode and re-send?

Click OK to confirm.

Manually Approved

or

Client Approved

Declined

If you change the status of a Manually Approved or Client Approved document to Declined, a Warning! confirmation popup opens:

Warning! This Change Order was already approved. You will not be able to edit this once declined. Are you sure you want to proceed?

Click OK to confirm.